Purchase, construction, engineering and installation of four floating steel pontoons with access bridge for refueling the passenger ports of Lengeh and Shahid Haqqani along with piling and construction of concrete foundation.

The Initial Scope of The Contract
  • Buy all materials
  • Construction of four metal floating docks
  • Construction of 4 metal access bridges with a length of approximately 20 meters
  • Painting (marine paint) of metal piers, access bridges and piles
  • Driving 8 tubular steel piles
  • Carry to the destination all the items and install them
  • Construction of 4 concrete foundations
  • Installation of bumpers and construction and installation of holders
  • Purchase all safety accessories and requirements of the docks, including electricity and lighting, salt and fresh water and…
Extra work

Major repairs of 3 floating metal piers of Shahid Haqqani Dam and their metal piles
Equipment used by the contractor

Company yards, labor and engineering camps, trailers, barges, cranes, forklifts, insoles, welding machines, blasting and paint equipment, sheds, cars, vans and other necessary equipment in the project.