• Project Name: Design, purchase, construction and installation of oil quay (35,000 tons) Hara Qeshm
  • Client: Pasargad Energy Development Co. (PEDC)
  • Location: Qeshm Island - Hara
  • Year of project completion: 2021
  • Links: Pasargad Energy Development Co. (PEDC)

Supply of equipment, supply of materials and construction of offshore structures of Qeshm sub-oil wharf (35,000 tons) including construction of a wharf with structural system, steel piles and steel deck and operating platform located in the north of Qeshm Island, Dargahan to Laft road, Kaveh industrial town Includes preparation of materials, construction of steel piles and piling, construction of prefabricated concrete parts and execution of concrete on site to create the deck, as well as preparation, transportation and installation of shock absorbers, bollards or QRH.

  • Heavy steel work includes making, transporting and knocking 52 and 40 inch steel piles
  • Procurement of materials, construction and installation of three steel bridges for access to dolphins with a length of about 40 meters
  • Procurement of materials, construction and installation of huge steel piles
  • Procurement of materials, construction and installation of handrails with all accessories
  • Preparation and transportation of materials and execution of concrete foundations
  • Preparation of marine paint materials, blasting and painting of sheet steel beams, piles, piles and access bridges in several layers
  • Prepare, transport and install several massive Fender
Equipment used by the contractor

Company yards, labor and engineering camps, tow trucks, barges, cranes, forklifts, insoles, welding machines, blasting and paint equipment, sheds, cars, vans and other necessary equipment.